Since handing over the site to the contractor on 28th March 2024, there has been steady progress in the work being undertaken. As of June, major ongoing work on-site includes the preparation of road bases for temporary access, excavation of detention pond, and site preparation for offices of contractors and consultants. Construction of accommodations for workers is also in progress. Site hoarding works are also being carried out.
Piling and foundation works are actively in progress. Driving of spun piles is advancing well, and so are the works for micro piling.
We can look forward to substantial progress over the next 3 to 4 months, and by then, site preparation and piling work should have been completed.